NEWS CONSTRUCTION UPDATE MAY 2017

Construction Update May 2017

16th May 2017

Significant progress has been made onsite at Curlewis Parks, with construction across all current stages progressing well despite some inclement weather in recent weeks.

STAGE 11

Following some delays from the recent wet weather, the civil works are now nearing completion. Footpaths and other concrete works are underway, as are the final earthworks on lots. Final roadworks will also commence shortly. The current completion date is the end of May, with title registration forecast for the end of June once the final approvals are received from Council and the Servicing Authorities.

STAGE 12

Works have commenced on site with earthworks well underway. Over the coming weeks this phase of construction will shape the commencement of civil works for Stage 12. The current forecast completion date is late October, with titles expected in November.

STAGE 17A

Approvals are in place and tender prices have now been received for the balance of civil works for Stage 17A. These works are expected to commence in June (to build on the preliminary on site works already completed), with a forecast completion date of late October and title registration in November.