NEWS FEBRUARY 2017 CONSTRUCTION UPDATE

February 2017 Construction Update

7th Mar 2017

STAGE 11

Sewer, water and drainage works now completed. Roads are formed up with kerb and channel to be constructed shortly, followed by electrical and NBN pit and pipe installation.

The estimated completion date for the civil works is mid April, with title registration forecast for mid May 2017.

STAGE 12

The approvals are now all in place and the required details to enable commencement of work to start are being put in place. The civil works for Stage 12 will also include some initial works for the Curlewis Park. The full landscape works will follow the completion of the civil works later this year.

Civil works are forecast to start on site by late March, with an estimated completion time of September 2017.

STAGE 17

The design of Stage 17 engineering details is completed with approvals being sought from Council and the servicing authorities.

Construction is forecasted to commence on site by June, with completion estimated for December 2017.